Posted by gold_12th on Thu Dec 18 02:31:01 2014 MTA is reporting 76% of the SAS phase 1 construction is completed. They are on target for December 2016 opening day.63 Street station finish... 85% is completed It will open the 63rd Street and Third Avenue entrance in upcoming months. New ADA elevators and escalators at that entrance. More info: http://web.mta.info/capital/sas_pdf/SAS%20Newsletter%2063rd-Dec_2014.pdf Schedule to complete: Summer 2015. 72 Street station finish 37% completed Issue: entrance at 69th Street is behind schedule. Contractor is implementing an agreed to mitigation plan to recover previously lost time with the Entrance #1 work. However, Contractor has recently encountered 21 days of delay with removal of the rock at the top of escalator incline which will require additional mitigation. More info: http://web.mta.info/capital/sas_pdf/SAS%20Newsletter%2072nd-Dec_2014.pdf Schedule to complete: JUNE 2016. 86 Street station finish 24% completed more info: http://web.mta.info/capital/sas_pdf/SAS%20Newsletter%2086th-Dec_2014.pdf Schedule to complete: JUNE 2016. 96 Street station finish 95% completed MTA is installing escalators from mezzanine to subway platform. Next phase is systems contract. http://web.mta.info/capital/sas_pdf/SAS%20Newsletter%2096th-Dec_2014.pdf Schedule to complete: Summer 2016. |
|
(1328909) | |
Re: Second Avenue Subway - December 2014 update |
|
Posted by italianstallion on Thu Dec 18 17:32:35 2014, in response to Second Avenue Subway - December 2014 update, posted by gold_12th on Thu Dec 18 02:31:01 2014. If 96th is 95% complete, why not finished till summer 2016? Couldn't they start service just to 96th even if 72 and 86 are not open yet? |
|
(1328922) | |
Re: Second Avenue Subway - December 2014 update |
|
Posted by The Silence on Thu Dec 18 18:51:32 2014, in response to Re: Second Avenue Subway - December 2014 update, posted by italianstallion on Thu Dec 18 17:32:35 2014. because the missing work at 72nd and 86th might include components necessary for the train to get to 96th..? |
|
(Sponsored) |
iPhone 6 (4.7 Inch) Premium PU Leather Wallet Case - Red w/ Floral Interior - by Notch-It
|
(1328930) | |
Re: Second Avenue Subway - December 2014 update |
|
Posted by randyo on Thu Dec 18 19:58:24 2014, in response to Re: Second Avenue Subway - December 2014 update, posted by The Silence on Thu Dec 18 18:51:32 2014. But what if it doesn’t? 23/Ely Av stood unopened for many years after the IND Queens Line opened and I believe there were a few WMATA stations that had to remain closed only because their elevators to make them ADA compliant were not ready. If it’s only a matter of station finish ot access, then the SAS to 96St could be opened with trains bypassing the unfinished stations. |
|
(1328932) | |
Re: Second Avenue Subway - December 2014 update |
|
Posted by italianstallion on Thu Dec 18 19:59:35 2014, in response to Re: Second Avenue Subway - December 2014 update, posted by randyo on Thu Dec 18 19:58:24 2014. Exactly. |
|
(1328935) | |
Re: Second Avenue Subway - December 2014 update |
|
Posted by zuckie13 on Thu Dec 18 20:08:59 2014, in response to Second Avenue Subway - December 2014 update, posted by gold_12th on Thu Dec 18 02:31:01 2014. At this rate it'll open before the 7 line extension... |
|
(1328936) | |
Re: Second Avenue Subway - December 2014 update |
|
Posted by The Silence on Thu Dec 18 20:12:30 2014, in response to Re: Second Avenue Subway - December 2014 update, posted by italianstallion on Thu Dec 18 19:59:35 2014. So you're ok with them on absolute block for about a mile and a half? |
|
(1328978) | |
Re: Second Avenue Subway - December 2014 update |
|
Posted by italianstallion on Fri Dec 19 00:16:47 2014, in response to Re: Second Avenue Subway - December 2014 update, posted by The Silence on Thu Dec 18 20:12:30 2014. Well, they should have signals at least. |
|
(1328998) | |
Re: Second Avenue Subway - December 2014 update |
|
Posted by MainR3664 on Fri Dec 19 07:21:48 2014, in response to Re: Second Avenue Subway - December 2014 update, posted by randyo on Thu Dec 18 19:58:24 2014. The tilework at 23/Ely was obviously different- I could see that even when I was 8 years old. I guess this explains it. When did the station open? |
|
(1329035) | |
Re: Second Avenue Subway - December 2014 update |
|
Posted by randyo on Fri Dec 19 12:43:01 2014, in response to Re: Second Avenue Subway - December 2014 update, posted by italianstallion on Fri Dec 19 00:16:47 2014. Correct. I would think that if there is signal equipment at 96 St that the line would be signaled all the way from 63 St. I’m only referring to lack of specific station amenities. It seem ed form the post that the only problem was that certain station entrances were not yet completed so that shouldn’t present any problem. In fact there is no reason why a station can’t be opened with only one entrance available rather than waiting for both to be completed. |
|