Feds Order Audit Of MTA East Side Access Project

Posted by Gold_12TH on Mon May 21 13:46:14 2012

edf40wrjww2msgDetail:detailStr
fiogf49gjkf0d
The effort to bring Long Island Rail Road trains to Manhattan's East Side will soon come under increased scrutiny from the feds.

U.S. Department of Transportation Inspector General Calvin L. Scovel III says he will begin an audit of the East Side Access project later this month.

The audit is being done because of cost overruns and delays with the project, which the federal government is helping to fund.

The Metropolitan Transportation Authority is also expected to announce today a new completion date and the latest price increase for the project.

It will eventually link Long Island Rail Road to Grand Central Terminal and affect hundreds of thousands of commuters.
---http://manhattan.ny1.com/content/top_stories/161629/feds-order-audit-of-mta-east-side-access-project

Post a New Response

(1157711)

view threaded

Re: Feds Order Audit Of MTA East Side Access Project

Posted by Olog-hai on Mon May 21 13:58:05 2012, in response to Feds Order Audit Of MTA East Side Access Project, posted by Gold_12TH on Mon May 21 13:46:14 2012.

edf40wrjww2msgDetail:detailStr
fiogf49gjkf0d
Hmm. Wonder if they would have audited ARC too if that had proceeded. Probably would have. Back during the days when Alternative G was still among the options considered for ARC, the cost estimates were below $3 billion.

Post a New Response

(1157713)

view threaded

Re: Feds Order Audit Of MTA East Side Access Project

Posted by randyo on Mon May 21 14:11:18 2012, in response to Feds Order Audit Of MTA East Side Access Project, posted by Gold_12TH on Mon May 21 13:46:14 2012.

edf40wrjww2msgDetail:detailStr
fiogf49gjkf0d
Maybe the Feds should audit the SAS also!

Post a New Response

(Sponsored)

iPhone 6 (4.7 Inch) Premium PU Leather Wallet Case - Red w/ Floral Interior - by Notch-It

(1157714)

view threaded

Re: Feds Order Audit Of MTA East Side Access Project

Posted by Olog-hai on Mon May 21 14:12:07 2012, in response to Re: Feds Order Audit Of MTA East Side Access Project, posted by randyo on Mon May 21 14:11:18 2012.

edf40wrjww2msgDetail:detailStr
fiogf49gjkf0d
You feel it's overpriced too . . . ?

Post a New Response

(1157810)

view threaded

Re: Feds Order Audit Of MTA East Side Access Project

Posted by WillD on Tue May 22 00:28:17 2012, in response to Re: Feds Order Audit Of MTA East Side Access Project, posted by Olog-hai on Mon May 21 13:58:05 2012.

edf40wrjww2msgDetail:detailStr
fiogf49gjkf0d
Only because it was massively underestimated. Read the EIS sometime. The engineers came to the inescapable conclusion that any effort tunneling that shallow under Manhattan was doomed to cost billions of dollars. You are not in any way qualified to question their conclusion.

Post a New Response

(1157846)

view threaded

Re: Feds Order Audit Of MTA East Side Access Project

Posted by Mr RT on Tue May 22 07:45:02 2012, in response to Feds Order Audit Of MTA East Side Access Project, posted by Gold_12TH on Mon May 21 13:46:14 2012.

edf40wrjww2msgDetail:detailStr
fiogf49gjkf0d
The problem is that even though they are now about one Billion over budget, they are so far along in the project that the only possible outcome would be that the Feds cut off the money & kill the project 3/4 complete.

Where were they 5 years ago ?

The problem seems to be that once the momentum of the project got going everybody jumped on to get a piece of the pork :-)

Post a New Response

(1157984)

view threaded

Re: Feds Order Audit Of MTA East Side Access Project

Posted by NIMBYkiller on Tue May 22 20:06:17 2012, in response to Re: Feds Order Audit Of MTA East Side Access Project, posted by Olog-hai on Mon May 21 13:58:05 2012.

edf40wrjww2msgDetail:detailStr
fiogf49gjkf0d
Definitely was my favorite of the options, but perhaps what Will explained is right

Post a New Response

(1158052)

view threaded

Re: Feds Order Audit Of MTA East Side Access Project

Posted by RIPTA42HopeTunnel on Wed May 23 08:19:15 2012, in response to Re: Feds Order Audit Of MTA East Side Access Project, posted by randyo on Mon May 21 14:11:18 2012.

edf40wrjww2msgDetail:detailStr
fiogf49gjkf0d
Maybe the Feds should audit the SAS also!

They are, and also the Fulton Transit Center. It's a routine audit that was scheduled more than two years ago.

FTA Oversight Announcement.

Post a New Response

(1158071)

view threaded

Re: Feds Order Audit Of MTA East Side Access Project

Posted by mshull on Wed May 23 10:44:39 2012, in response to Feds Order Audit Of MTA East Side Access Project, posted by Gold_12TH on Mon May 21 13:46:14 2012.

edf40wrjww2msgDetail:detailStr
fiogf49gjkf0d
So basically, the Feds are auditing themselves.

They are paying a huge share of the cost, and they (Amtrak) are the ones who are not letting the LIRR into the Sunnyside/Harold area to do the work.

Quit screwing around already, and get along with yourself!

Post a New Response

(1158073)

view threaded

Re: Feds Order Audit Of MTA East Side Access Project

Posted by RIPTA42HopeTunnel on Wed May 23 10:58:58 2012, in response to Re: Feds Order Audit Of MTA East Side Access Project, posted by mshull on Wed May 23 10:44:39 2012.

edf40wrjww2msgDetail:detailStr
fiogf49gjkf0d
So basically, the Feds are auditing themselves.

That's what the Office of the Inspector General does. If the feds weren't paying for it there would be no grounds for an audit.