Posted by randyo on Wed May 4 17:41:35 2016, in response to Re: Split M/T during (L) tunnel closure, posted by Joe V on Wed May 4 12:21:56 2016. The problem is that CBTC work is being done by an outside contractor and the time frames for completion of the work are spelled out in the contract. In many cases there are penalties against the contractor for delays in completing the work, so conversely, the contractor could very well penalize the MTA for delaying its work as well. |