Re: A way to maintain peak service into Penn in case of North River tunnel closure |
|
Posted by Outside the Box on Wed Oct 22 18:05:08 2014, in response to Re: A way to maintain peak service into Penn in case of North River tunnel closure, posted by Bill from Maspeth on Wed Oct 22 17:02:02 2014. This plan doesn't cycle trains. AM rush NJT to NY Penn runs one way and layup at Sunnyside Yards. Those trains run Jerseybound during PM Peak. The Limiting factor is the number of trains the Yard can hold and open track spaces at NY Penn to hold trains Midday.The setup probably makes for 12tph Peak direction. |