MTA actually trying to claim that Amtrak work is delaying ESA

Posted by Olog-hai on Wed Aug 16 14:03:40 2017

edf40wrjww2msgDetail:detailStr
No details on just how, though. (From a couple of weeks ago)

News 12 Lawn Guyland

MTA: Amtrak work causing delays in East Side Access project

Posted: Jul 24, 2017 5:31 PM EDT
Updated: Jul 24, 2017 5:55 PM EDT
The MTA says Amtrak's summer work at Penn Station is causing delays for the ongoing East Side Access project.

Once complete, the East Side Access project is expected to help minimize the impact when there are railroad problems and Penn Station troubles by giving commuters another option to get to Grand Central Station.

"East Side Access has been delayed so many years many people believe it will never happen," says Charles Moerdler, of the MTA. "If East Side Access had opened on time, there would not be the 'Summer of Hell.'"

Transit officials say 162,000 are expected to use the East Side Access daily when it's finally complete.

But at Monday's MTA board meeting, officials said the project is being delayed by the Amtrak infrastructure work.

However, MTA officials said that so far, Amtrak's work is proceeding on schedule. About two weeks into the two-month project, it is now about 30 percent complete overall.


Post a New Response

(1446698)

view threaded

Re: MTA actually trying to claim that Amtrak work is delaying ESA

Posted by Joe V on Wed Aug 16 14:18:11 2017, in response to MTA actually trying to claim that Amtrak work is delaying ESA, posted by Olog-hai on Wed Aug 16 14:03:40 2017.

edf40wrjww2msgDetail:detailStr
I don't see how. All the work is west of the Penn Station platforms and replacing track 10 - 12, all places that seldom feel the weight of a LIRR train, yet their rush hour train volume is down 18%.

I think MTA is making excuses for ESA. Of course they could have done some minimal improvements at Hunterspoint Ave, given how they fucked up planning and engineering requirements for ESA so badly.

Post a New Response

(1446699)

view threaded

Re: MTA actually trying to claim that Amtrak work is delaying ESA

Posted by Dutchrailnut on Wed Aug 16 14:22:46 2017, in response to Re: MTA actually trying to claim that Amtrak work is delaying ESA, posted by Joe V on Wed Aug 16 14:18:11 2017.

edf40wrjww2msgDetail:detailStr
due to Amtrak MofW forces being all employed at NYP, work at Harold is severely being delayed

Post a New Response

(Sponsored)

iPhone 6 (4.7 Inch) Premium PU Leather Wallet Case - Red w/ Floral Interior - by Notch-It

(1446708)

view threaded

Re: MTA actually trying to claim that Amtrak work is delaying ESA

Posted by Joe V on Wed Aug 16 15:26:47 2017, in response to Re: MTA actually trying to claim that Amtrak work is delaying ESA, posted by Dutchrailnut on Wed Aug 16 14:22:46 2017.

edf40wrjww2msgDetail:detailStr
OK, so it's a labor supply issue.

Post a New Response

(1446723)

view threaded

Re: MTA actually trying to claim that Amtrak work is delaying ESA

Posted by SUBWAYMAN on Wed Aug 16 16:32:52 2017, in response to Re: MTA actually trying to claim that Amtrak work is delaying ESA, posted by Joe V on Wed Aug 16 14:18:11 2017.

edf40wrjww2msgDetail:detailStr
The MTA is not kidding. They don't control the work on Amtrak trackage.

Post a New Response

(1446733)

view threaded

Re: MTA actually trying to claim that Amtrak work is delaying ESA

Posted by Olog-hai on Wed Aug 16 18:47:09 2017, in response to Re: MTA actually trying to claim that Amtrak work is delaying ESA, posted by Dutchrailnut on Wed Aug 16 14:22:46 2017.

edf40wrjww2msgDetail:detailStr
What does that have to do with ESA? Looks like that has its own Harold bypass and is not dependent on Amtrak at all.

Post a New Response

(1446735)

view threaded

Re: MTA actually trying to claim that Amtrak work is delaying ESA

Posted by Olog-hai on Wed Aug 16 18:50:08 2017, in response to Re: MTA actually trying to claim that Amtrak work is delaying ESA, posted by Joe V on Wed Aug 16 15:26:47 2017.

edf40wrjww2msgDetail:detailStr
So the MTA contributes nothing at all to Harold's upkeep, even though they are the primary user? Doesn't sound right to me. Never mind the connection of ESA to Harold being an MTA project and nothing to do with Amtrak.

Post a New Response

(1446736)

view threaded

Re: MTA actually trying to claim that Amtrak work is delaying ESA

Posted by Dutchrailnut on Wed Aug 16 18:50:35 2017, in response to Re: MTA actually trying to claim that Amtrak work is delaying ESA, posted by Olog-hai on Wed Aug 16 18:47:09 2017.

edf40wrjww2msgDetail:detailStr
how little you know...


Post a New Response

(1446737)

view threaded

Re: MTA actually trying to claim that Amtrak work is delaying ESA

Posted by Dutchrailnut on Wed Aug 16 18:50:35 2017, in response to Re: MTA actually trying to claim that Amtrak work is delaying ESA, posted by Olog-hai on Wed Aug 16 18:47:09 2017.

edf40wrjww2msgDetail:detailStr
how little you know...


Post a New Response

(1446739)

view threaded

Re: MTA actually trying to claim that Amtrak work is delaying ESA

Posted by Dutchrailnut on Wed Aug 16 18:51:38 2017, in response to Re: MTA actually trying to claim that Amtrak work is delaying ESA, posted by Joe V on Wed Aug 16 15:26:47 2017.

edf40wrjww2msgDetail:detailStr
correct, no people to do the work required for ESA.
they are at the NYP project.

Post a New Response

(1446740)

view threaded

Re: MTA actually trying to claim that Amtrak work is delaying ESA

Posted by Joe V on Wed Aug 16 18:57:20 2017, in response to Re: MTA actually trying to claim that Amtrak work is delaying ESA, posted by Olog-hai on Wed Aug 16 18:50:08 2017.

edf40wrjww2msgDetail:detailStr
Harold Interlocking's upkeep has nothing to do with ESA construction. The first is an operational issue, the other is a capital expansion. Amtrak's cooperation is required for tunneling perpendicular under Sunnyside Yard and the Harold Flyover project. Amtrak trains to New Haven will use that.


Post a New Response

(1446741)

view threaded

Re: MTA actually trying to claim that Amtrak work is delaying ESA

Posted by Joe V on Wed Aug 16 19:00:25 2017, in response to Re: MTA actually trying to claim that Amtrak work is delaying ESA, posted by Olog-hai on Wed Aug 16 18:47:09 2017.

edf40wrjww2msgDetail:detailStr
It has everything to do with both railroads, including Amtrak's bread and butter (Acela), and is the busiest railroad junction in the country.

Too bad is was not built with Pennsy-style under-jumps or flyovers in the first place like they have further east where the Port Washington Branch and Hell Gate line split off, and at White Pot.

Post a New Response

(1446745)

view threaded

Re: MTA actually trying to claim that Amtrak work is delaying ESA

Posted by Andrew Saucci on Wed Aug 16 19:43:39 2017, in response to MTA actually trying to claim that Amtrak work is delaying ESA, posted by Olog-hai on Wed Aug 16 14:03:40 2017.

edf40wrjww2msgDetail:detailStr
The Amtrak work certainly can't help, but sometimes it seems as though every gust of wind delays ESA.

Post a New Response

(1446753)

view threaded

Re: MTA actually trying to claim that Amtrak work is delaying ESA

Posted by Olog-hai on Wed Aug 16 21:10:11 2017, in response to Re: MTA actually trying to claim that Amtrak work is delaying ESA, posted by Andrew Saucci on Wed Aug 16 19:43:39 2017.

edf40wrjww2msgDetail:detailStr
Especially the gusts of wind within corporate in Jamaica.

Post a New Response

(1446764)

view threaded

Re: MTA actually trying to claim that Amtrak work is delaying ESA

Posted by Buddsilverliner269 on Thu Aug 17 06:00:06 2017, in response to Re: MTA actually trying to claim that Amtrak work is delaying ESA, posted by SUBWAYMAN on Wed Aug 16 16:32:52 2017.

edf40wrjww2msgDetail:detailStr
Amtrak DOES NOT own Harold interlocking. LIRR does. Amtrak owns the Hell Gate line and the tunnels into NYP but does not own Harold. Yes Amtrak dies do maintenance work on Harold and many have been pulled to do the NYP track project but please tell me how this has anything to do with ESA project when they are still doing fun so work and no track work or Signal work?

Post a New Response

(1446813)

view threaded

Re: MTA actually trying to claim that Amtrak work is delaying ESA

Posted by SUBWAYMAN on Thu Aug 17 19:23:14 2017, in response to Re: MTA actually trying to claim that Amtrak work is delaying ESA, posted by Buddsilverliner269 on Thu Aug 17 06:00:06 2017.

edf40wrjww2msgDetail:detailStr
My point is that every problem that happens with ESA is not always the MTA's fault, sometimes outside forces like Amtrak are to blame. IMHO the MTA does a far better job than they get credited for.