Re: Nassau Street connection to SAS |
|
|
Posted by Wallyhorse on Wed Feb 13 06:15:18 2008, in response to Re: Nassau Street connection to SAS, posted by Russ on Tue Feb 12 14:20:22 2008. So:If necessary, you terminate the J at Chambers (as is already done on weekends), and make the T a through-train to Bay Parkway at all times (with J passengers having a same or cross-platform transfer in that scenario). I also had previously said that if necessary, some T trains can terminate at Houston Street (until Water Street can be built) if that is an issue so the J can continue to Broad. The point is, the T going via Nassau to Bay Parkway can be ready YEARS before the Water Street part of the SAS can be ready. |