Posted by JRice on Fri May 4 13:13:01 2007, in response to Re: New details on East Side Access construction; photos, posted by Sand Box John on Fri May 4 09:30:19 2007. CM009 will be about the same diameter. No rock crusher and muck will be hauled by a conveyor through the existing tunnel, up above grade at the bellmouth, acorss Northern Blvd in an enclosed bridge supporting the conveyor and out into Yard A. Whether it will be crushed, I do not know yet. The original plan was for rail haul, but NYAR does not seem very interested. That is too bad because the material can be hauled out for use all over LI.The muck from the Queens tunnels will be contaminated with VOC's and will have to got to NJ or Pennsylvania, likely by truck. |