| Re: Queens Super Express Alignment (1555432) | |||
|
|
|||
| Home > SubChat | |||
|
[ Read Responses | Post a New Response | Return to the Index ] |
|
||
Re: Queens Super Express Alignment |
|
|
Posted by jamestrains1 on Wed Aug 12 01:31:36 2020, in response to Re: Queens Super Express Alignment, posted by jamestrains1 on Wed Aug 12 01:16:58 2020. I recently came across an interesting image showing tunnel alignments through Sunnyside yard. This is a very outdated image from an environmental document produced in the preliminary engineering stages for the East Side Access project, circa early 2002. Most, if not all of the tunnel alignments have since been altered prior to their construction.Now, while the image below does a poor job of showing the Super Express tunnel alignments, it does clearly show the aborted "planned" NYCT yard lead in green. ![]() Source: ENVIRONMENTAL STATUS AND CONSTRUCTION PLAN for the QUEENS ALIGNMENT MTA East Side Access Project - January 2002 ENVIRONMENTAL STATUS AND CONSTRUCTION PLAN for the QUEENS ALIGNMENT see PDF pg.50 |