Re: Completion of Historic LIRR Double Track More Than a Year Ahead of Schedule

Posted by GP38/R42 Chris on Sun Sep 23 14:31:03 2018, in response to Re: Completion of Historic LIRR Double Track More Than a Year Ahead of Schedule, posted by Steamdriven on Sat Sep 22 00:15:37 2018.

????

First off, Wyandanch only had one platform for both directions, so an entire new platform as well as crossover, elevators, etc had to be added.
Second, in many spots, while there was room for a second track, it was necessary to grade for the track, etc.
Not to mention signalling and electrical work.
Not to mention actual laying of the track.
Grade crossing widening and upgrades.
All being done while trying minimum disruption to existing trains on the other track.

(There are no responses to this message.)