Re: IRT Platform Extension Dates (1368733) | |||
Home > SubChat | |||
[ Read Responses | Post a New Response | Return to the Index ] |
|
Re: IRT Platform Extension Dates |
|
Posted by randyo on Sat Oct 3 14:18:09 2015, in response to Re: IRT Platform Extension Dates, posted by Steve B-8AVEXP on Fri Oct 2 19:37:19 2015. That was only on the 7 Av expresses. The ridership on the west side was such that 9 car trains could be operated on the expresses until the platforms were extended. Lex was a different story, so Lo-Vs had to be operated on the expresses during the week until all platforms were extended to 10 cars since 9 car trains wouldn’t have carried the loads. |