LIRR M-9 Screw Up (1358884) | |||
Home > SubChat | |||
[ Read Responses | Post a New Response | Return to the Index ] |
|
LIRR M-9 Screw Up |
|
Posted by R2Chinatown on Tue Jul 7 21:47:08 2015 Apparently, there was a design deficiency in the M-9 railcars than will likely delay the delivery. LIRR engineers allocated just 8 Sq ft of space for the PTC equipment but the equipment now required by the Federal Government requires 17 Sq. Ft.Note: If this was posted in another thread and I missed it - to bad. |