(6 to 12 month delay) More info on BOMBardier R-179 welding crack prototype cars issue (1304513) | |||
Home > SubChat | |||
[ Read Responses | Post a New Response | Return to the Index ] |
|
(6 to 12 month delay) More info on BOMBardier R-179 welding crack prototype cars issue |
|
Posted by Gold_12th on Mon Jul 28 16:54:52 2014, in response to Re: More info on BOMBardier R-179 welding crack prototype cars issue, posted by Gold_12th on Mon Jul 28 16:37:25 2014. Original schedule...Awarded: 6/04/2012 Delivery of test train: 12/22/2014 -- delay forecasted Delivery of 1st Production unit: 7/27/2015 Delivery Completion: 1/30/2017 New schedule delivery 6 months or 12 months Delivery of test train: June 2015 or December 2015 Delivery of 1st Production unit: January 2016 or July 2016 Delivery Completion: July 2017 or January 2018 |